Osceola County will begin numerous road resurfacing projects in the Poinciana area on Monday, October 5. Work will be performed daily from 8 a.m. to 5 p.m., and schedules may vary based on weather conditions or equipment-related issues. There will be temporary lane closures but no road closures, and traffic delays can be expected in the area.

Monday October 5 through Friday October 9
· Windmill Point Boulevard: Pleasant Hill Road to Lanesboro Street

Monday October 12 through Friday October 16
· Fountainbleu Boulevard: Pleasant Hill Road to Victoria Drive
· Victoria Drive: Fountainbleu Boulevard to Fountainbleu Boulevard
· Trevi Court: Fountainbleu Boulevard to cul-de-sac

Monday October 19 through Friday October 30
· Cypressview Court:Pine Needle Trail to cul-de-sac
· Evergreen Court: Pine Needle Trail to cul-de-sac
· Fern Court: Pine Needle Trail to cul-de-sac
· Foxboro Court: Pine Needle Trail to cul-de-sac
· Longleaf Court: Pine Needle Trail to cul-de-sac
· Mahogany Court: Pine Needle Trail to cul-de-sac
· Pine Needle Trail: Pleasant Hill Road to Lake Tohopekaliga Boulevard
· Pinewood Court: Pine Needle Trail to cul-de-sac
· Sawgrass Court: Pine Needle Trail to cul-de-sac
· Shadow Wood Court: Pine Needle Trail to cul-de-sac
· Shortleaf Court: Pine Needle Trail to cul-de-sac
· Woodsmere Court: Pine Needle Trail to cul-de-sac
· Lake Tohopekaliga Boulevard: North Stewart Street north to end of pavement

Work will be performed daily from 8 a.m. to 5 p.m. Schedules may vary based on weather conditions or equipment-related issues. There will be temporary lane closures but no road closures, and traffic delays can be expected in the area.